Jakkur Lake Constructed-Wetland Rejuvenation — Bengaluru's Sewage-to-Ecosystem-Service Water Fund

India · Bengaluru · See the India profile · See the Bengaluru profile

Evidence: Observational / pre–post Top 53% 47/100 · Ask Evidence Copilot about this practice

Bengaluru's state development authority built a ~4.6-hectare constructed wetland to treat 10 million litres/day of sewage before it reaches Jakkur Lake, cutting BOD 66% and COD 45%, restoring habitat for 197 recorded bird species and livelihoods for 70 fishing families.

10 million litres/day
Sewage treated daily
4.6 ha
Constructed wetland area
66 %
Biochemical Oxygen Demand removal
45 %
Chemical Oxygen Demand removal
Jakkur Lake Constructed-Wetland Rejuvenation — Bengaluru's Sewage-to-Ecosystem-Service Water Fund

Details

Maturity
Established
Promoter
Bangalore Development Authority (BDA) / Bruhat Bengaluru Mahanagara Palike (BBMP) / Jala Poshan Trust
Period
2008 (wetland construction) – present
Keywords
water management, wetland restoration, wastewater treatment, biodiversity

Context

Like many of Bengaluru's roughly 200 urban lakes, Jakkur Lake had become a dumping ground for untreated sewage by the 2000s. In 2008 the Bangalore Development Authority, with support from the Karnataka Power Corporation Limited for the treatment plant, built an integrated wastewater-to-wetland system to intercept sewage before it reaches the lake.

Activities

A UASB treatment plant handles about 10 million litres of sewage a day, feeding a roughly 4.6-hectare constructed wetland of macrophyte beds (Typha, Cyperus, water hyacinth and others) and an algal polishing basin before the water reaches the lake. Since around 2014, day-to-day maintenance has been run by the community-based Jala Poshan trust — six women from self-help groups plus fishers — funded by donor contributions and BBMP allocations rather than direct fees, since BBMP rules bar official income-generating activity at the lake.

Results

Published water-quality monitoring found the wetland's first treatment stage removes roughly 45% of Chemical Oxygen Demand, 66% of Biochemical Oxygen Demand, 33% of nitrate-nitrogen and 40% of phosphate, and testing of around 300 nearby borewells found rising water levels and lower nitrate concentrations within half a kilometre of the lake. The restored lake now supports approximately 197 recorded bird species, including nesting spot-billed pelicans, and sustains about 70 fishing families and 30 cattle-owning or grass-cutting families, with fishers reporting catches of up to 500kg on good days.

Conclusions

The model is now cited as a template for other Bengaluru lakes, but its funding is patchwork and maintenance-dependent (roughly 1.5–2 lakh INR/month raised informally) rather than backed by a guaranteed public payment stream, and researchers caution that without secure long-term financing, wetland performance and community stewardship arrangements like Jakkur's can be difficult to sustain or replicate at scale.

Implementation

Indicative cost
Medium (€50k–€500k) — Municipal capital investment in the treatment plant and wetland, with a modest (~1.5–2 lakh INR/month) informally raised maintenance budget.
Time to results
Long (> 3 years) — Constructed in 2008; continuous operation and community maintenance since then, about 18 years.
Staffing & skills
Bangalore Development Authority (BDA), Karnataka Power Corporation Limited (treatment plant support), Bruhat Bengaluru Mahanagara Palike (BBMP), Jala Poshan trust (community maintenance — six women from self-help groups plus fishers)

Conditions for success

  • Integrated UASB treatment plant, constructed wetland and algal polishing basin design
  • Community-based maintenance trust (Jala Poshan) operating since around 2014
  • Donor contributions and BBMP allocations supplementing maintenance funding

Common failure modes

  • Funding is patchwork and informally raised (~1.5–2 lakh INR/month) rather than a guaranteed public payment stream, which researchers flag as a barrier to sustaining or replicating the model at scale
  • BBMP rules bar official income-generating activity at the lake, limiting fee-based funding options

Commonly funded by

National / regional programmes Own resources / municipal budget

Indicative funding routes for practices of this type — always check each programme's current calls and eligibility rules.

Do you run this practice? Claim it — verified implementers get a public contact pathway and can propose corrections.

Data sources

Where this practice's information was retrieved from, and when.

Attachments

Similar practices you may find useful