Al Zohour Green Triangle — Nature-Based Flood Mitigation Pilot, Amman

Jordan · Amman · See the Jordan profile · See the Amman profile

Evidence: Descriptive / self-reported Top 96% 20/100 · Ask Evidence Copilot about this practice

UN-Habitat and Greater Amman Municipality built a $465,000, 2,300 m² nature-based drainage pilot at Ras Al-Ain — bioswales plus an underground storage tank capturing peak flood flows — as a replicable blueprint for 120 flash-flood-risk points mapped across Amman.

120 points
Flood-risk points mapped across Amman
2300 m2
Pilot site area
750 m3 (approx.)
Bioretention/bioswale capacity
2,100-2,500 m3
Underground storage tank capacity
465000 USD
Total implementation cost
Al Zohour Green Triangle — Nature-Based Flood Mitigation Pilot, Amman

Details

Maturity
Pilot
Promoter
UN-Habitat Jordan / Greater Amman Municipality (funded by the Government of Japan)
Period
2020–2022 (built); operational since May 2022
Keywords
urban green infrastructure, sustainable urban drainage (SUDS), flood mitigation, bioswale

Context

Amman's dense, hilly urban fabric channels flash floods through narrow valleys, and the city has mapped 120 high flood-risk points. The Al Zohour Green Triangle pilot in the Ras Al-Ain district, funded by the Government of Japan and delivered by UN-Habitat Jordan with the Greater Amman Municipality, was built between April 2020 and November 2022 and inaugurated on 31 May 2022.

Objectives

Demonstrate a nature-based drainage model that can substitute or supplement costly grey infrastructure at other flood-risk points across Amman.

Activities

The 2,300 m2 site replaces part of the area's grey drainage with a sustainable urban drainage system (SUDS): vegetated bioretention basins and bioswales feeding an underground detention/storage tank that slows and holds peak flows for later reuse via a pump system.

Results

The bioswales provide roughly 750 m3 of retention capacity, feeding an underground tank reported as 2,100-2,500 m3 across sources. Total implementation cost was about USD 465,000.

Conclusions

This is a single 2,300 m2 pilot; no independent hydrological performance study or grey-vs-green avoided-cost calculation has been published, underground tank capacity is reported inconsistently across otherwise credible sources, and there is no public confirmation yet that any of the other 119 mapped sites have been built.

Implementation

Indicative cost
Low (< €50k) — USD 465,000 total implementation cost for the 2,300 m2 pilot.
Time to results
Medium (1–3 years) — Built April 2020 - November 2022; inaugurated 31 May 2022.
Staffing & skills
UN-Habitat Jordan (delivery), Greater Amman Municipality (delivery partner), Government of Japan (funder)

Conditions for success

  • Bilateral funding partnership (Government of Japan) plus municipal delivery capacity
  • Prior mapping of flood-risk points across the city to prioritise pilot siting

Common failure modes

  • No independent hydrological evaluation published
  • Underground tank capacity reported inconsistently across sources
  • No public confirmation yet of replication at the other 119 mapped sites

Do you run this practice? Claim it — verified implementers get a public contact pathway and can propose corrections.

Data sources

Where this practice's information was retrieved from, and when.

Attachments

Similar practices you may find useful

★ 60

New York City Catskills watershed protection

United States of America

Rather than build an $8–10bn filtration plant, New York City invests in protecting its Catskill/Delaware watershed — ~$2.5bn since 1997 …