KISIP — Kenya's Informal Settlements Improvement Project

Kenya · Nairobi · See the Kenya profile · See the Nairobi profile

Evidence: Observational / pre–post Top 34% 76/100 · Ask Evidence Copilot about this practice

Kenya's national informal-settlements upgrading programme has prepared over 23,000 land titles and delivered roads, drainage, water and sewer connections that the government reports have reached over 1.3 million residents since 2011.

23,397 titles
Land titles prepared (Phase 1) (2011–)
26,387 households
Households directly benefiting (2011–)
~110,820 households
Households indirectly benefiting (2011–)
1.3M+ residents
Total residents benefited (2011–)
98.3 km
Bitumen roads built (2011–)
120 km
Footpaths built (2011–)
~110 km
Drainage canals built (2011–)
165 million USD
Phase 2 financing (2011–2026)
KISIP — Kenya's Informal Settlements Improvement Project

Details

Maturity
Established
Promoter
State Department for Housing and Urban Development, Government of Kenya, with the World Bank, Sida and AFD
Period
2011–2026
Keywords
housing, land tenure, urban infrastructure, informal settlements

Context

Launched in 2011 with co-financing from the World Bank, Sweden's Sida and the French Development Agency (AFD), the Kenya Informal Settlements Improvement Project (KISIP) set out to improve tenure security and infrastructure in informal settlements, growing from 15 urban centres in 14 counties under Phase 1 (2011) to 81 settlements across 33 counties under the roughly US$165 million Phase 2, due to close in 2026.

Activities

Phase 1 prepared land titles and delivered infrastructure works including bitumen roads, footpaths, drainage canals, and combined sewer and water pipelines and connections. The approach was formally mainstreamed into Kenya's National Slum Upgrading and Prevention Policy in 2016.

Results

Phase 1 prepared 23,397 land titles benefiting 26,387 households directly and around 110,820 households indirectly, with infrastructure works — 98.3km of bitumen roads, 120km of footpaths, roughly 110km of drainage canals, over 100km of combined sewer and water pipelines, and thousands of new water and sewer connections — reported to have benefited more than 1.3 million residents in total.

Conclusions

World Bank Implementation Status and Results reports have independently tracked disbursement and physical progress against these targets, though as with most large tenure-regularisation programmes, land titling has generally proceeded more slowly than the infrastructure works in several counties.

Implementation

Indicative cost
Very high (> €5M)
Time to results
Long (> 3 years)
Staffing & skills
State Department for Housing and Urban Development, Government of Kenya, World Bank, Sweden's Sida, French Development Agency (AFD), county governments

Conditions for success

  • Multi-donor co-financing (World Bank, Sida, AFD) sustained across two phases
  • Formal mainstreaming into national policy (2016 National Slum Upgrading and Prevention Policy) to lock in institutional replication
  • Phased geographic scale-up (14 to 33 counties) rather than a single big-bang rollout

Common failure modes

  • Land titling has generally proceeded more slowly than infrastructure works in several counties

Where it fits

Governance type
national government with multilateral/bilateral co-financing
Scale
national (33 counties)
Income level
lower-middle-income

Commonly funded by

National / regional programmes

Indicative funding routes for practices of this type — always check each programme's current calls and eligibility rules.

Do you run this practice? Claim it — verified implementers get a public contact pathway and can propose corrections.

Data sources

Where this practice's information was retrieved from, and when.

Attachments

Similar practices you may find useful