Arase Dam Removal — Japan's First Full Concrete Dam Demolition on the Kuma River, With Measured Channel Recovery but Mixed Ecological Evidence (Kumamoto, Japan)

Japan · Yatsushiro · See the Japan profile

Top 72% 33/100 · Ask Evidence Copilot about this practice

Kumamoto Prefecture removed the 25 m Arase hydropower dam (2012-2018), Japan's first full concrete dam removal. Studies found channel changes within about 4 km of the site, new gravel-bar habitat and more fast-water invertebrates, but no significant effect on estuary benthos.

Details

Promoter
Kumamoto Prefecture (Enterprise Bureau)
Period
2010-2018 (gates opened 2010; demolition April 2012-March 2018)
Keywords
river restoration, dam removal, sediment continuity, freshwater biodiversity, hydropower decommissioning

Description

The Arase Dam was a 25 m high gravity dam with a 210.8 m crest and movable gates, built by Kumamoto Prefecture on the Kuma River at Yatsushiro. It began producing power in 1954 and at first met 16% of the prefecture's electricity demand, a share that fell steadily over time. After local calls for its removal, the prefecture chose removal when the dam's water rights expired in 2010. The gates were opened, and demolition by staged blasting ran from April 2012 to March 2018. It was Japan's first full removal of a concrete dam and won the Japan Federation of Construction Contractors' civil engineering award.
Measured effects: analysis of monitoring-camera images showed the water level at the dam site fell by about 4 m. Changes to the main river channel were confined to about 4 km upstream and downstream, and the river bed below a downstream weir became sandier with no silt deposits (Morii et al., 2020). After a flood in June 2015, a new gravel bar formed downstream. It increased shallow habitat, raised average baseflow velocity by about 1.8 times, and increased invertebrate species that prefer faster currents. Flow seeping through the bar fed a backwater with higher species richness than before (Kobayashi et al., 2016). Environmental-DNA work also suggested ayu habitat was recovering in the former reservoir section.
Caveats: a 2011-2018 survey of the Kuma and Mae river estuaries (14 surveys, 138 sites) concluded that the removal probably had no significant impact on the estuarine benthic community. Sediment became coarser and infaunal species increased in 2012-2014, but the authors say the link to the dam removal is not fully verified (Koyama et al., 2022). Physical recovery is well documented, while biological gains are local and modest. The prefecture compiled an environmental monitoring report in 2020. Severe flooding in July 2020 hit Hitoyoshi upstream, but the evaluators found the removal had not contributed to inundation around the former dam site.

Read the full analysis: https://www.nikkenren.com/publication/ACe/ce/ace2105/pdf/p30-31_202105.pdf

Implementation

Implementation detail (cost, timeline, staffing, conditions for success) is not yet available for this practice.

Do you run this practice? Claim it — verified implementers get a public contact pathway and can propose corrections.

Data sources

Where this practice's information was retrieved from, and when.

Similar practices you may find useful