evidoria

← Back to browse

Good practice Imported

Houtan Park — Constructed Wetland Water Treatment on a Reclaimed Shanghai Brownfield

China · Shanghai · See the China profile · See the Shanghai profile

Evidence: Descriptive / self-reported Top 33% 53/100 · Ask Evidence Copilot about this practice

A 14-hectare former steel-mill and shipyard on Shanghai's Huangpu River was rebuilt as a 1-mile constructed wetland that biologically treats ~2,400 tonnes of river water a day, lifting it from Grade V to Grade II/III while buffering floods.

14 hectares
Site area
~1.7 km
Wetland length
~2,400 tonnes/day
Water treated daily
Grade V to Grade II/III
Water quality improvement
93
Plant species documented
200+
Animal species documented
~242 tonnes
Estimated CO2 sequestered annually
~116,800 USD/year
Estimated water-cost savings
8
Patents generated
20-30
Later projects informed
Houtan Park — Constructed Wetland Water Treatment on a Reclaimed Shanghai Brownfield

Details

Maturity
Established
Promoter
Turenscape (Kongjian Yu), for the Shanghai Expo Coordination Bureau
Period
2007–2010 design/construction; operating since 2010
Keywords
landscape architecture, wastewater treatment, brownfield remediation, urban parks

Context

Houtan Park occupies a 14-hectare brownfield on the south bank of the Huangpu River in Pudong, Shanghai — formerly a steel factory and shipyard — redesigned by Turenscape (led by Kongjian Yu) for the 2010 Shanghai World Expo and kept afterward as a public riverfront park.

Activities

Its centerpiece is a roughly 1-mile-long (1.7 km), 5-30 metre-wide constructed wetland: river water is diverted through a series of cascading, terraced wetland cells planted with species selected for pollutant uptake, using settling, aeration and microbial processes to purify it entirely without chemical treatment. The park also replaced a 22-foot concrete floodwall with a graded riprap edge that functions as a buffer between 20-year and 1,000-year flood-control levees.

Results

The Landscape Performance Series case study reports the wetland treats roughly 2,400 tonnes (about 634,000 gallons) of water per day, raising it from Grade V (unfit for human contact) to Grade II/III (suitable for irrigation and non-potable reuse); 93 plant species and over 200 animal species have been documented on site, and the same source estimates roughly 242 tonnes of CO2 sequestered annually and about $116,800/year in water-cost savings for an adjacent facility. The design won ASLA's 2010 Award of Excellence and, per Turenscape, produced 8 patents and informed 20-30 later projects.

Conclusions

The detailed treatment-capacity, carbon and cost figures trace to a single design-firm-submitted case study (assessed under the Landscape Performance Series' own methodology) rather than an independent government water-quality audit, so they should be read as credible but not independently re-verified.

Implementation

Indicative cost
Medium (€50k–€500k)
Time to results
Medium (1–3 years)
Staffing & skills
Turenscape (Kongjian Yu) — design firm, Shanghai Expo Coordination Bureau — commissioning authority

Conditions for success

  • designing for a fixed high-profile deadline (the 2010 Shanghai World Expo) to secure funding and political will
  • replacing hard flood infrastructure (a concrete floodwall) with a graded, ecologically functional edge
  • publishing a detailed design case study, which has itself supported the model's transfer to 20-30 later projects

Common failure modes

  • the detailed treatment-capacity, carbon and cost figures trace to a single design-firm-submitted case study rather than an independent government water-quality audit, so they should be read as credible but not independently re-verified

Commonly funded by

National / regional programmes

Indicative funding routes for practices of this type — always check each programme's current calls and eligibility rules.

Do you run this practice? Claim it — verified implementers get a public contact pathway and can propose corrections.