After five drainage attempts shrank Lake Hornborga from 28 km² to under 4 km² of open water, Sweden cleared ~1,200 ha of reed and ~800 ha of trees and raised the level ~0.9 m (1992–95); 299 bird species are now recorded, but published before/after counts are scarce.

Lake Hornborga Restoration — Re-Raising a Five-Times-Drained Swedish Bird Lake, 1992–1995 (Sweden)

Details

Promoter
Länsstyrelsen Västra Götaland (County Administrative Board of Västra Götaland)
Period
1965–1995 (restoration works 1992–1995)
Keywords
lake restoration, wetland rewetting, Ramsar, birds, grazing, nature reserve

Description

Lake Hornborga (Hornborgasjön), a shallow lake between Falköping and Skara in Västergötland, was lowered five times from 1802 onwards to win pasture and farmland. The lake did not yield good farmland; instead reeds and scrub spread, and the open-water area fell from about 28 km² to less than 4 km² after the final drainage in 1933.
The site was among Sweden's first Ramsar designations (1974). Following a 1965 government investigation and a later government decision, one of Sweden's largest nature-conservation projects removed about 1,200 ha of reed and 800 ha of trees and shrubs, reintroduced grazing on the shores and raised the water level by an average of about 0.9 m between 1992 and 1995, aiming at a self-sustaining bird lake resembling conditions of 1877–1904.
Reported outcomes: the Swedish Environmental Protection Agency states that bird populations grew quickly after the level was raised; 299 bird species have been reported, the lake supports threatened ferruginous duck, black tern and black-necked grebe, thousands of cranes stage there each spring, and the reserve draws about 250,000 visitors a year. A field station has run annual breeding-bird inventories as restoration follow-up.
Caveats: the raise was scaled back from the original plan, and a formal evaluation of whether goals were met (University of Skövde, funded by the Swedish EPA, 2013–2016) is documented but its quantified results were not located for this entry; much of the public evidence is agency reporting rather than peer-reviewed before/after analysis. Restoration cost is not published in the sources reviewed.

Read the full analysis: https://www.naturvardsverket.se/om-oss/aktuellt/nyheter-och-pressmeddelanden/2026/augusti/fran-utdikad-sjo-till-naturikon-naturum-hornborgasjon-firar-40-ar/

Implementation

Implementation detail (cost, timeline, staffing, conditions for success) is not yet available for this practice.

Do you run this practice? Claim it — verified implementers get a public contact pathway and can propose corrections.

Data sources

Where this practice's information was retrieved from, and when.

Attachments

Similar practices you may find useful