Lusaka Sanitation Project — World Bank-Financed Sewer Upgrading for Zambia's Capital

Zambia · Lusaka · See the Zambia profile · See the Lusaka profile

Evidence: Observational / pre–post Top 61% 67/100 · Ask Evidence Copilot about this practice

A $65M World Bank-financed programme rehabilitated and extended Lusaka's sewer network, connecting 345,000+ residents to sanitation services -- beating its 305,000 target -- while cutting sewer-fault response times from 28% to 100% resolved within 48 hours.

65 million USD
World Bank IDA credit (2015–2024)
345,000+ people
Residents gaining sanitation access (target: 305,000) (2015–2024)
2,200+ connections
New household sewer connections (2015–2024)
117 km
Sewer lines rehabilitated or built (2015–2024)
3,500 facilities
Improved on-site sanitation facilities constructed (2015–2024)
264,000 people
People with access to improved fecal sludge management (Manchinchi plant) (2015–2024)
28 %
Sewer-blockage complaints resolved within 48 hours, before project (before project)
100 %
Sewer-blockage complaints resolved within 48 hours, after project (2024)

Details

Maturity
Established
Promoter
Lusaka Water and Sanitation Company (LWSC)
Period
2015-2024
Keywords
sanitation, water infrastructure, informal settlements, public utilities

Context

Between 2015 and 2024, Zambia's Lusaka Water and Sanitation Company (LWSC) used a $65 million World Bank IDA credit — plus $3.5 million in Government of Zambia counterpart funding and $390,000 in technical assistance from the Global Water Security & Sanitation Partnership — to rehabilitate and extend sewer infrastructure across priority sewersheds in Lusaka, including the Manchinchi and Ngwerere catchments serving the city's dense peri-urban settlements.

Activities

The project added over 2,200 new household sewer connections, rehabilitated or built 117 km of sewer lines, constructed 3,500 improved on-site sanitation facilities, and built the Manchinchi Fecal Sludge Treatment Plant, which brought 264,000 people access to improved fecal sludge management.

Results

The project exceeded its own targets: more than 345,000 residents (against a target of 305,000) gained access to improved sanitation, half of them women. Utility responsiveness improved sharply too: the share of sewer-blockage complaints resolved within 48 hours rose from 28% to 100%.

Conclusions

The project sits within Zambia's wider, still-expanding Lusaka Sanitation Programme (an estimated $300 million effort co-financed by the World Bank, African Development Bank, EU and KfW). Even on its own terms, though, the Lusaka Sanitation Project reached only about a sixth of Lusaka District's roughly 2.2 million residents, and its own resettlement action plan documents acknowledge construction encroaching on peri-urban land — vegetable gardens and boundary walls — used informally by residents along the works corridor. Large informal settlements elsewhere in the city remain largely outside the upgraded network, underlining that this is a well-executed but partial answer to Lusaka's sanitation gap, not a city-wide fix.

Implementation

Indicative cost
High (€500k–€5M) — Financed via a $65 million World Bank IDA credit, $3.5 million Government of Zambia counterpart funding, and $390,000 in GWSP technical assistance, 2015–2024.
Time to results
Long (> 3 years) — Delivered 2015–2024; sits within the wider, still-expanding $300 million Lusaka Sanitation Programme co-financed by the World Bank, African Development Bank, EU and KfW.
Staffing & skills
Lusaka Water and Sanitation Company (LWSC) — implementing utility, Zambia Ministry of Water Development and Sanitation, World Bank / IDA (financing), Global Water Security & Sanitation Partnership (technical assistance)

Conditions for success

  • Blended financing (IDA credit, government counterpart funds, and technical assistance) supported both capital works and utility capacity building
  • Targeting priority sewersheds serving dense peri-urban settlements concentrated investment where need was greatest

Common failure modes

  • The project's own resettlement action plan documents construction encroaching on peri-urban land (vegetable gardens, boundary walls) used informally by residents along the works corridor
  • Coverage reached only about a sixth of Lusaka District's population, leaving large informal settlements outside the upgraded network

Commonly funded by

National / regional programmes ERDF — European Regional Development Fund

Indicative funding routes for practices of this type — always check each programme's current calls and eligibility rules.

Do you run this practice? Claim it — verified implementers get a public contact pathway and can propose corrections.

Data sources

Where this practice's information was retrieved from, and when.

Similar practices you may find useful